Filters
Question type

Study Flashcards

The overhead cost per unit of Product S under activity-based costing is closest to:


A) $1.83.
B) $1.98.
C) $5.00.
D) $10.00.

E) B) and D)
F) A) and C)

Correct Answer

verifed

verified

Batch-level activities are performed each time a batch is handled or processed,regardless of how many units are in the batch.

A) True
B) False

Correct Answer

verifed

verified

Matt Company uses activity-based costing.The company has two products: A andB.The annual production and sales of Product A are 8,000 units and of Product B are 6,000 units.There are three activity cost pools,with estimated total cost and expected activity as follows: Matt Company uses activity-based costing.The company has two products: A andB.The annual production and sales of Product A are 8,000 units and of Product B are 6,000 units.There are three activity cost pools,with estimated total cost and expected activity as follows:   The cost per unit of Product A under activity-based costing is closest to: A)  $2.40. B)  $3.90. C)  $6.60. D)  $10.59. The cost per unit of Product A under activity-based costing is closest to:


A) $2.40.
B) $3.90.
C) $6.60.
D) $10.59.

E) B) and C)
F) All of the above

Correct Answer

verifed

verified

Setting up equipment is an example of a:


A) unit-level activity.
B) batch-level activity.
C) product-level activity.
D) facility-level activity.

E) A) and D)
F) B) and C)

Correct Answer

verifed

verified

The overhead cost per unit of Product B under the traditional costing system is closest to:


A) $5.49.
B) $11.45.
C) $26.09.
D) $50.66.

E) B) and C)
F) All of the above

Correct Answer

verifed

verified

Using activity-based costing is not useful in determining costs of quality.

A) True
B) False

Correct Answer

verifed

verified

Testing a prototype of a new product is an example of a:


A) unit-level activity.
B) batch-level activity.
C) product-level activity.
D) facility-level activity.

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

Suki Company uses activity-based costing to compute product costs for external reports.The company has three activity cost pools and applies overhead using predetermined overhead rates for each activity cost pool.Estimated costs and activities for the current year are presented below for the three activity cost pools: Suki Company uses activity-based costing to compute product costs for external reports.The company has three activity cost pools and applies overhead using predetermined overhead rates for each activity cost pool.Estimated costs and activities for the current year are presented below for the three activity cost pools:   Actual activity for the current year was as follows:   The amount of overhead applied for Activity 3 during the year was closest to A)  $30,026.50. B)  $35,773.45. C)  $36,107.00. D)  $36,112.00. Actual activity for the current year was as follows: Suki Company uses activity-based costing to compute product costs for external reports.The company has three activity cost pools and applies overhead using predetermined overhead rates for each activity cost pool.Estimated costs and activities for the current year are presented below for the three activity cost pools:   Actual activity for the current year was as follows:   The amount of overhead applied for Activity 3 during the year was closest to A)  $30,026.50. B)  $35,773.45. C)  $36,107.00. D)  $36,112.00. The amount of overhead applied for Activity 3 during the year was closest to


A) $30,026.50.
B) $35,773.45.
C) $36,107.00.
D) $36,112.00.

E) A) and C)
F) None of the above

Correct Answer

verifed

verified

Bridget Company uses activity-based costing.The company has two products: A andB.The annual production and sales of Product A are 2,000 units and of Product B are 3,000 units.There are three activity cost pools,with estimated total cost and expected activity as follows: Bridget Company uses activity-based costing.The company has two products: A andB.The annual production and sales of Product A are 2,000 units and of Product B are 3,000 units.There are three activity cost pools,with estimated total cost and expected activity as follows:   The cost per unit of Product A under activity-based costing is closest to: A)  $6.40. B)  $8.63. C)  $9.60. D)  $13.80. The cost per unit of Product A under activity-based costing is closest to:


A) $6.40.
B) $8.63.
C) $9.60.
D) $13.80.

E) None of the above
F) All of the above

Correct Answer

verifed

verified

Assuming that actual activity turns out to be the same as expected activity,the total amount of overhead cost allocated to Product X would be closest to:


A) $235,000.
B) $316,600.
C) $357,500.
D) $563,000.

E) All of the above
F) A) and B)

Correct Answer

verifed

verified

Facility-level costs can be easily and accurately allocated to different products using activity-based costing.

A) True
B) False

Correct Answer

verifed

verified

Which of the following would be considered as a prevention cost?


A) Inspection of completed products prior to shipment to customers.
B) Supplier management.
C) Rework costs.
D) Scrap costs.

E) None of the above
F) B) and D)

Correct Answer

verifed

verified

When there are batch-level or product-level costs,in comparison to a traditional cost system,an activity-based costing system ordinarily will shift costs from high-volume to low-volume products.

A) True
B) False

Correct Answer

verifed

verified

Overhead allocation based on volume alone:


A) is a key aspect of the activity-based costing model.
B) will systematically overcost high-volume products and undercost low-volume products.
C) will systematically overcost low-volume products and undercost high-volume products.
D) must be used for external financial reporting.

E) None of the above
F) A) and C)

Correct Answer

verifed

verified

The activity rate for Activity 3 is closest to:


A) $26.67.
B) $56.74.
C) $116.18.
D) $119.72.

E) A) and D)
F) A) and C)

Correct Answer

verifed

verified

The overhead cost per unit of Product B under the activity-based costing system is closest to


A) $26.09.
B) $35.28.
C) $38.16.
D) $50.66.

E) A) and D)
F) B) and C)

Correct Answer

verifed

verified

Which of the following is not a limitation of activity-based costing?


A) More accurate product costs may result in better decisions.
B) Changing from a traditional direct labour based costing system to an activity-based costing system changes product margins and other key performance indicators used by managers.
C) Implementing an activity based costing system is more costly than implementing a traditional direct labour-based costing system.
D) In practice,most managers insist on fully allocating all costs to products,customers,and other costing objects in an activity based costing system.This results in overstated costs.

E) B) and C)
F) A) and B)

Correct Answer

verifed

verified

Departmental overhead rates applied on the basis of a volume measure such as direct labour-hours or machine-hours will eliminate any distortions in unit costs due to product diversity.

A) True
B) False

Correct Answer

verifed

verified

Unit-level activities are performed each time a unit is made.

A) True
B) False

Correct Answer

verifed

verified

The activity rate computed at the beginning of the year for the batch setup activity cost pool is closest to:


A) $54.50.
B) $71.80.
C) $74.00.
D) $197.60.

E) B) and C)
F) A) and C)

Correct Answer

verifed

verified

Showing 21 - 40 of 98

Related Exams

Show Answer