A) $22 million
B) $34 million
C) $35 million
D) $24 million
Correct Answer
verified
Multiple Choice
A) $3.00
B) $1.05
C) $50.25
D) $17.60
Correct Answer
verified
Multiple Choice
A) 11.1%
B) 10.8%
C) 9.6%
D) 10.5%
Correct Answer
verified
Multiple Choice
A) The APV approach explicitly values the market imperfections and therefore allows managers to measure their contribution to value.
B) We need to know the debt level to compute the APV, but with a constant debt-equity ratio we need to know the project's value to compute the debt level.
C) The WACC method is more complicated than the APV method because we must compute two separate valuations: the unlevered project and the interest tax shield.
D) Implementing the APV approach with a constant debt-equity ratio requires solving for the project's debt and value simultaneously.
Correct Answer
verified
Multiple Choice
A) 10.3%
B) 10.0%
C) 9.5%
D) 9.9%
Correct Answer
verified
Multiple Choice
A) The WACC can be used throughout the firm as the company wide cost of capital for new investments that are of comparable risk to the rest of the firm and that will not alter the firm's debt-equity ratio.
B) A disadvantage of the WACC method is that you need to know how the firm's leverage policy is implemented to make the capital budgeting decision.
C) The intuition for the WACC method is that the firm's weighted average cost of capital represents the average return the firm must pay to its investors (both debt and equity holders) on an after-tax basis.
D) To be profitable, a project should generate an expected return of at least the firm's weighted average cost of capital.
Correct Answer
verified
Multiple Choice
A) $63 million
B) $50 million
C) $167 million
D) $100 million
Correct Answer
verified
Multiple Choice
A) If the debt-equity ratio changes over time, the risk of equity-and, therefore, its cost of capital-will change as well.
B) The FTE method can offer an advantage when calculating the value of equity for the entire firm, if the firm's capital structure is complex and the market values of other securities in the firm's capital structure are not known.
C) The FTE approach does not have the same disadvantage associated with the APV approach: We don't need to compute the project's debt capacity to determine interest and net borrowing before we can make the capital budgeting decision.
D) The WACC and APV methods compute the firm's enterprise value, so that a separate valuation of the other components of the firm's capital structure is needed to determine the value of equity.
Correct Answer
verified
Multiple Choice
A) $25 million
B) $60 million
C) $45 million
D) $40 million
Correct Answer
verified
Multiple Choice
A) the required rate of return on debt.
B) the dollar amount of equity.
C) the after tax required rate of return on debt.
D) the required rate of return on equity.
Correct Answer
verified
Multiple Choice
A) The project's free cash flow to equity shows the expected amount of additional cash the firm will have available to pay dividends (or conduct share repurchases) each year.
B) The value of the project's FCFE should be identical to the NPV computed using the WACC and APV methods.
C) The value of the project's FCFE represents the gain to shareholders from the project.
D) Because interest payments are deducted before taxes, we adjust the firm's FCF by their before-tax cost.
Correct Answer
verified
Multiple Choice
A) $5 million
B) $100 million
C) -$100 million
D) -$50 million
Correct Answer
verified
Multiple Choice
A) 5.0%
B) 12%
C) 15.0%
D) 17.0%
Correct Answer
verified
Multiple Choice
A) $150 million
B) $180 million
C) $230 million
D) $240 million
Correct Answer
verified
Multiple Choice
A) $195 million
B) $200 million
C) $235 million
D) $240 million
Correct Answer
verified
Multiple Choice
A) Because the WACC incorporates the tax savings from debt, we can compute the levered value of an investment, which is its value including the benefit of interest tax shields given the firm's leverage policy, by discounting its future free cash flow using the WACC.
B) The WACC incorporates the benefit of the interest tax shield by using the firm's before-tax cost of capital for debt.
C) When the market risk of the project is similar to the average market risk of the firm's investments, then its cost of capital is equivalent to the cost of capital for a portfolio of all of the firm's securities; that is, the project's cost of capital is equal to the firm's weighted average cost of capital (WACC) .
D) A project's cost of capital depends on its risk.
Correct Answer
verified
Multiple Choice
A) When we relax the assumption of a constant debt-equity ratio, the FTE method is relatively straightforward to use and is therefore the preferred method with alternative leverage policies.
B) When debt levels are set according to a fixed schedule, we can discount the predetermined interest tax shields using the debt cost of capital, rD.
C) With a constant interest coverage policy, the value of the interest tax shield is proportional to the project's unlevered value.
D) When the firm keeps its interest payments to a target fraction of its FCF, we say it has a constant interest coverage ratio.
Correct Answer
verified
Multiple Choice
A) $100 million
B) $120 million
C) $124 million
D) $115 million
Correct Answer
verified
Multiple Choice
A) Compute the value of the investment, including the tax benefit of leverage, by discounting the free cash flow of the investment using the WACC.
B) Compute the weighted average cost of capital.
C) Determine the free cash flow of the investment.
D) Adjust the WACC for the firm's current debt/equity ratio.
Correct Answer
verified
Multiple Choice
A) $10 million
B) $13 million
C) $42 million
D) $71 million
Correct Answer
verified
Showing 1 - 20 of 96
Related Exams