Filters
Question type

Study Flashcards

The fixed overhead volume variance measures the use of existing facilities and capacity.

A) True
B) False

Correct Answer

verifed

verified

A flexible budget is a summary of expected costs for a range of activity levels and is geared to changes in the level of productive output.

A) True
B) False

Correct Answer

verifed

verified

The primary difference between a fixed (static) budget and a flexible budget is that a fixed budget


A) cannot be changed after the period begins, whereas a flexible budget can be changed after the period begins.
B) is concerned only with future acquisitions of fixed assets, whereas a flexible budget is concerned with expenses that vary with sales.
C) is a plan for a single level of production, whereas a flexible budget is several plans (one for each of several production levels) .
D) includes only fixed costs, whereas a flexible budget includes only variable costs.

E) A) and C)
F) None of the above

Correct Answer

verifed

verified

A flexible budget is most useful


A) for budgeting and planning purposes.
B) when actual output equals budgeted output.
C) as a cost control tool to help evaluate performance.
D) when a product's cost structure includes variable costs only.

E) None of the above
F) A) and B)

Correct Answer

verifed

verified

The direct materials price standard is determined by averaging costs of current purchases.

A) True
B) False

Correct Answer

verifed

verified

Standard costs are useful for all but which of the following?


A) Determining actual costs
B) Preparing budgets and forecasts
C) Evaluating the performance of workers and management
D) Helping to develop appropriate selling prices

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

The direct labor rate variance is the difference between actual hours worked and standard hours allowed for good units produced,multiplied by the standard labor rate.

A) True
B) False

Correct Answer

verifed

verified

Ewing Corporation's controller has developed the cost and usage data listed below in preparation of standard unit cost information for the coming year.  Direct materials quantity standard 3 pounds per product  Direct labor time standard 5 hours per product  Direct materials price standard $10 per pound  Direct labor rate standard $9 per hour  Standard variable overhead rate $5 per labor hour  Standard fixed overhead rate $10 per labor hour \begin{array}{lr} \text { Direct materials quantity standard } & 3 \text { pounds per product } \\\text { Direct labor time standard } & 5 \text { hours per product } \\\text { Direct materials price standard } & \$ 10 \text { per pound } \\\text { Direct labor rate standard } & \$ 9 \text { per hour } \\\text { Standard variable overhead rate } & \$ 5 \text { per labor hour } \\\text { Standard fixed overhead rate } & \$ 10 \text { per labor hour }\end{array} The standard unit cost for overhead is


A) $15.
B) $25.
C) $50.
D) $75.

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

The direct materials price variance is the difference between the actual price and the standard price,multiplied by the standard quantity.

A) True
B) False

Correct Answer

verifed

verified

In standard costing,


A) the standards are developed only for overhead costs.
B) the standards are developed primarily from past costs.
C) comparisons with actual costs usually are not performed.
D) debit and credit entries to inventory accounts are made at standard costs.

E) A) and D)
F) All of the above

Correct Answer

verifed

verified

If actual capacity used exceeds expected capacity,the fixed overhead volume variance is favorable.

A) True
B) False

Correct Answer

verifed

verified

Underfoot Products uses standard costing.The following information about overhead was generated during May:  Standard variable overhead rate $2 per machine howr  Standard fixed overhead rate $1 per machine hour  Actual variable overhead costs $390,000 Actual Eixed dverhead costs $175,000 Budgeted fixed overhead costs $190,000 Standard machine hours per urit produced 10 Good urits produced 18,000 Actual machine hours 200,000\begin{array} { l l } \text { Standard variable overhead rate } & \$ 2 \text { per machine howr } \\\text { Standard fixed overhead rate } & \$ 1 \text { per machine hour } \\\text { Actual variable overhead costs } & \$ 390,000 \\\text { Actual Eixed dverhead costs } & \$ 175,000 \\\text { Budgeted fixed overhead costs } & \$ 190,000 \\\text { Standard machine hours per urit produced } & 10 \\\text { Good urits produced } & 18,000 \\\text { Actual machine hours } & 200,000\end{array} Compute the fixed overhead variance.


A) $5,000 (F)
B) $5,000 (U)
C) $10,000 (U)
D) $10,000 (F)

E) None of the above
F) B) and D)

Correct Answer

verifed

verified

The Lennon Company uses a standard costing system and a flexible budget.At a normal level of activity of 15,000 units and 45,000 standard direct labor hours,the standard direct labor cost would be $270,000.During June,44,050 hours were worked to produce 14,000 units at an actual direct labor cost of $352,000.The direct labor efficiency variance in June was


A) $20,300 (U) .
B) $12,300 (U) .
C) $12,300 (F) .
D) $15,300 (U) .

E) A) and B)
F) None of the above

Correct Answer

verifed

verified

The overhead variance is equal to the difference between


A) fixed overhead costs and flexible overhead costs.
B) estimated overhead rate and applied overhead rate.
C) actual overhead costs and variable overhead costs.
D) actual overhead costs and standard overhead costs.

E) None of the above
F) C) and D)

Correct Answer

verifed

verified

The direct materials standards for the main product of Duchess Company are 8 grams of direct materials per product at a cost of $3 per gram.During April,974 grams of direct materials were used to produce 120 products at a direct materials cost of $2,900.The direct materials quantity variance for April was


A) $72 (U) .
B) $92 (U) .
C) $42 (U) .
D) $112 (F) .

E) A) and D)
F) A) and B)

Correct Answer

verifed

verified

Sweet Dreams manufactures candy.Its records revealed the following data:  Number of urits produced 4,000 Standard direct labor hours per unit 2 Standard variable overhead rate $2.50 per hour  Standard fixed overhead rate $5.00 per hour  Budgeted fixed overhead costs $40,800 Actual variable overhead costs $16,800 Actual fixed overhead costs $40,400 Actual labor hours 8,000 direct labor hours  Total actual overhead $57,200\begin{array} { l l } \text { Number of urits produced } & 4,000 \\\text { Standard direct labor hours per unit } & 2 \\\text { Standard variable overhead rate } & \$ 2.50 \text { per hour } \\\text { Standard fixed overhead rate } & \$ 5.00 \text { per hour } \\\text { Budgeted fixed overhead costs } & \$ 40,800 \\\text { Actual variable overhead costs } & \$ 16,800 \\\text { Actual fixed overhead costs } & \$ 40,400 \\\text { Actual labor hours } & 8,000 \text { direct labor hours } \\\text { Total actual overhead } & \$ 57,200\end{array} The total variable overhead variance is


A) $3,200 (U) .
B) $3,200 (F) .
C) $3,600 (F) .
D) $0.

E) All of the above
F) A) and B)

Correct Answer

verifed

verified

A direct labor rate variance would occur in which of the following situations?


A) When a production employee takes an unplanned break
B) When a production employee spends more time producing one product than was expected
C) When a low-paid production employee performs a task higher than his or her assigned level
D) When a production employee incurs overtime hours at the same hourly rate as regular pay

E) All of the above
F) A) and C)

Correct Answer

verifed

verified

The formula used to compute budgeted total cost at any level of activity is presented in the


A) flexible budget.
B) performance report.
C) static budget.
D) cash flow forecast.

E) B) and D)
F) A) and B)

Correct Answer

verifed

verified

Powerhorse,Inc.,manufactures steel hitches for horse trailers.The company's direct labor rates have been set by the terms of the current labor contract.Direct labor rate standards have been assigned for each job classification.In July 20xx,a young apprentice was being trained during regular working hours to become a machine operator on one of the turret lathes.A timekeeper determined that the apprentice had spent a total of 48 hours as a novice machine operator in July.Standard time for the same work output is 34 hours.The apprentice earned $6.80 per hour in July.The standard direct labor rate for machine operators working on turret lathes is $9.50 per hour. a. From the data provided, determine the direct labor efficiency variance and the direct labor rate variance that resulted from the temporary substitution of the apprentice for the regular machine operator. (Note that, according to the labor contract, the apprentice is not entitled to the same rate as a regular machine operator during the training period.) b. Did the company benefit financially from the situation? Why or why not? (Show calculations.)

Correct Answer

verifed

verified

a.Direct labor effic...

View Answer

If standard costing is not economically feasible for a company,predetermined overhead rates should not be used.

A) True
B) False

Correct Answer

verifed

verified

Showing 101 - 120 of 121

Related Exams

Show Answer