Filters
Question type

Study Flashcards

Sultzer Corporation applies manufacturing overhead to products on the basis of standard machine-hours. Budgeted and actual overhead costs for the most recent month appear below:  Original Budget Actual Costs  Fixed overhead costs: Supervision. $18,900$19,090 Utilities.3,4003,190Factory depreciation. 9,8009,660Total overhead cost $32,100$31,940\begin{array}{lrr}&\text { Original Budget }&\text {Actual Costs }\\\text { Fixed overhead costs: }\\\text {Supervision. }&\$ 18,900 & \$ 19,090 \\\text { Utilities.}&3,400 & 3,190 \\\text {Factory depreciation. }&9,800 & 9,660 \\\text {Total overhead cost }&\$ 32,100 & \$ 31,940 \\\end{array} The company based its original budget on 3,000 machine-hours. The company actually worked 2,730 machine-hours during the month. The standard hours allowed for the actual output of the month totaled 2,690 machine-hours. What was the overall fixed manufacturing overhead budget variance for the month?


A) $3,317 favorable
B) $160 unfavorable
C) $3,317 unfavorable
D) $160 favorable

E) None of the above
F) B) and D)

Correct Answer

verifed

verified

At the end of the year, actual manufacturing overhead costs were $110,000 and applied manufacturing overhead costs were $118,800. If the denominator activity for the year was 20,000 machine-hours, and if 22,000 standard machine-hours were allowed for the year's production, the predetermined overhead rate per machine-hour was:


A) $5.00
B) $5.94
C) $5.50
D) $5.40

E) A) and B)
F) B) and D)

Correct Answer

verifed

verified

How much overhead was applied to products during the period to the nearest dollar?


A) $44,712
B) $44,125
C) $43,125
D) $44,850

E) C) and D)
F) A) and D)

Correct Answer

verifed

verified

Krouse Corporation's manufacturing overhead includes $14.70 per machine-hour for variable manufacturing overhead and $191,580 per period for fixed manufacturing overhead. Required: Determine the predetermined overhead rate for the denominator level of activity of 3,100 machine-hours.

Correct Answer

verifed

verified

Predetermined overhead rate = Estimated ...

View Answer

The fixed element of the predetermined overhead rate was (per DLH) :


A) $4.15
B) $3.00
C) $2.00
D) $1.15

E) All of the above
F) None of the above

Correct Answer

verifed

verified

Walkenhorst Corporation's manufacturing overhead includes $7.80 per machine-hour for supplies; $7.30 per machine-hour for indirect labor; $21,210 per period for salaries; and $19,950 per period for depreciation. Required: Determine the predetermined overhead rate if the denominator level of activity is 1,500 machine-hours. Show your work!

Correct Answer

verifed

verified

Estimated total manufacturing overhead c...

View Answer

The variable overhead rate variance was:


A) $4,500 U
B) $10,500 U
C) $13,500 U
D) $16,500 U

E) A) and B)
F) B) and C)

Correct Answer

verifed

verified

A company has a standard cost system in which fixed and variable manufacturing overhead costs are applied to products on the basis of direct labor-hours. The company's choice of the denominator level of activity affects the Fixed component of the predetermined overhead rate.

A) True
B) False

Correct Answer

verifed

verified

The variable overhead efficiency variance for March is:


A) $8,000 favorable
B) $4,000 favorable
C) $8,000 unfavorable
D) $4,000 unfavorable

E) All of the above
F) B) and D)

Correct Answer

verifed

verified

Moralez Corporation has a standard cost system in which it applies manufacturing overhead to products on the basis of standard machine-hours (MHs) . The company has provided the following data for the most recent month: Moralez Corporation has a standard cost system in which it applies manufacturing overhead to products on the basis of standard machine-hours (MHs) . The company has provided the following data for the most recent month:   What was the total of the variable overhead rate and fixed manufacturing overhead budget variances for the month? A) $380 unfavorable B) $1,620 favorable C) $1,660 unfavorable D) $3,280 unfavorable What was the total of the variable overhead rate and fixed manufacturing overhead budget variances for the month?


A) $380 unfavorable
B) $1,620 favorable
C) $1,660 unfavorable
D) $3,280 unfavorable

E) B) and D)
F) B) and C)

Correct Answer

verifed

verified

The variable element of the predetermined overhead rate was (per DLH) :


A) $4.15
B) $3.00
C) $2.00
D) $1.15

E) B) and C)
F) A) and B)

Correct Answer

verifed

verified

The total predetermined overhead rate per machine-hour for November was:


A) $1.75
B) $2.40
C) $2.97
D) $1.40

E) A) and B)
F) All of the above

Correct Answer

verifed

verified

What was the fixed manufacturing overhead budget variance for the period to the nearest dollar?


A) $881 U
B) $484 U
C) $395 U
D) $1,500 F

E) All of the above
F) B) and D)

Correct Answer

verifed

verified

The variable overhead rate variance for March is:


A) $7,000 unfavorable
B) $9,000 unfavorable
C) $13,000 unfavorable
D) $11,000 unfavorable

E) A) and D)
F) A) and C)

Correct Answer

verifed

verified

The Clayton Company uses a standard cost system in which manufacturing overhead costs are applied to units of the company's single product on the basis of standard direct labor-hours (DLHs). The standard cost card for the product follows:  Standard Cost Card-per unit of product  Direct Materials, 4 yards at $ 3.50 per yard.$14 Direct Labor, 1.5 DLHs at $8 per DLH 12Variable Overhead, 1.5 DLHs at $2 per DLH 3Fixed Overhead, 1.5 DLHs at $6 per DLH 9 Standard cost per unit.$38\begin{array}{lr}\text { Standard Cost Card-per unit of product }\\\text { Direct Materials, 4 yards at \$ 3.50 per yard.}&\$ 14 \\\text { Direct Labor, 1.5 DLHs at \$8 per DLH }&12 \\\text {Variable Overhead, 1.5 DLHs at \$2 per DLH }&3 \\\text {Fixed Overhead, 1.5 DLHs at \$6 per DLH }&9 \\\text { Standard cost per unit.}&\$ 38 \\\end{array} The following data pertain to last year's activities: • The company manufactured 18,000 units of product during the year. A total of 70,200 yards of material was purchased during the year at a cost of $3.75 per yard. All of this material was used to manufacture the 18,000 units. • The company worked 29,250 direct labor-hours during the year at a cost of $7.80 per hour. • The denominator activity level was 22,500 direct labor-hours. • Budgeted fixed manufacturing overhead costs were $135,000 while actual manufacturing overhead costs were $133,200. • Actual variable overhead costs were $61,425. Required: a. Compute the direct materials price and quantity variances for the year. b. Compute the direct labor rate and efficiency variances for the year. c. Compute the variable overhead rate and efficiency variances for the year. d. Compute the fixed manufacturing overhead budget and volume variances for the year.

Correct Answer

verifed

verified

a. Direct materials price and quantity v...

View Answer

What was the fixed manufacturing overhead budget variance for the period to the nearest dollar?


A) $1,800 U
B) $222 F
C) $1,010 U
D) $785 U

E) None of the above
F) All of the above

Correct Answer

verifed

verified

What was the variable overhead rate variance for the period to the nearest dollar?


A) $1,750 U
B) $820 F
C) $1,750 F
D) $820 U

E) All of the above
F) C) and D)

Correct Answer

verifed

verified

Coskey Corporation applies manufacturing overhead to products on the basis of standard machine-hours. Budgeted and actual overhead costs for the month appear below:  Original Budget  Actual Costs  Variable overhead costs: Supplies. $16,770$16,150Indirect labor. 19,89018,910 Fixed overhead costs:  Supervision13,30013,540Utilities. 4,1004,100Factory depreciation 9,3009,380Total overhead cost $63,360$62,080\begin{array}{l}&\text { Original Budget }&\text { Actual Costs }\\\text { Variable overhead costs: }\\\text {Supplies. }&\$ 16,770 & \$ 16,150 \\\text {Indirect labor. }&19,890 & 18,910\\\text { Fixed overhead costs: }\\\text { Supervision}&13,300 & 13,540 \\\text {Utilities. }&4,100 & 4,100 \\\text {Factory depreciation }&9,300 & 9,380 \\\text {Total overhead cost }&\$ 63,360 & \$ 62,080 \\\end{array} The company based its original budget on 3,900 machine-hours. The company actually worked 3,580 machine-hours during the month. The standard hours allowed for the actual output of the month totaled 3,770 machine-hours. What was the overall fixed manufacturing overhead budget variance for the month?


A) $1,280 favorable
B) $320 favorable
C) $320 unfavorable
D) $1,280 unfavorable

E) A) and D)
F) B) and C)

Correct Answer

verifed

verified

The terms "standard quantity allowed" or "standard hours allowed" means:


A) the actual output in units multiplied by the standard output allowed.
B) the actual input in units multiplied by the standard output allowed.
C) the actual output in units multiplied by the standard input allowed.
D) the standard output in units multiplied by the standard input allowed.

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

The fixed manufacturing overhead applied to Franklin's production for the year is:


A) $484,200
B) $575,000
C) $594,000
D) $600,000

E) C) and D)
F) A) and D)

Correct Answer

verifed

verified

Showing 41 - 60 of 105

Related Exams

Show Answer