If a load report (resource requirements profile) shows a work centre scheduled beyond capacity


A) the company must add capacity by enlarging the facility.
B) the company must add capacity by such tactics as overtime and subcontracting.
C) the work centre's load may be smoothed by such tactics as operations splitting or lot splitting.
D) the aggregate plan must be revised.
E) the Wagner-Whitin algorithm should be used to rebalance the load.

F) B) and C)
G) A) and C)

Correct Answer

verifed

verified

If the explosion of the bill of material tells MRP how much of each part is needed,how does MRP learn when each of these parts is needed?

Correct Answer

verifed

verified

Timing is established with the time-phas...

View Answer

________ are a way of allowing a segment of the master schedule to be designated as "not to be rescheduled."

Correct Answer

verifed

verified

Operations splitting sends pieces to the next operation before the entire lot is completed on the previous operation.

A) True
B) False

Correct Answer

verifed

verified

A material requirements plan contains information with regard to all of the following except


A) quantities and required delivery dates of all subassemblies.
B) quantities and required delivery dates of final products.
C) the capacity needed to provide the projected output rate.
D) inventory on hand for each final product.
E) inventory on hand for each subassembly.

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

Describe the role of record accuracy in Wheeled Coach's successful use of MRP.Is this company's experience the exception or the rule? Answer in a well-developed paragraph.

Correct Answer

verifed

verified

Wheeled Coach's record integrity is exce...

View Answer

An engineering change notice is used to change a(n)


A) MRP.
B) MPS.
C) ERP.
D) BOM.
E) DRP.

F) A) and B)
G) C) and E)

Correct Answer

verifed

verified

The time-phased product structure,unlike the bill of material,adds the concept of lead times.

A) True
B) False

Correct Answer

verifed

verified

Closed-loop MRP systems allow production planners to move work between time periods to smooth the load or to at least bring it within capacity.

A) True
B) False

Correct Answer

verifed

verified

If parts and subassemblies common to a variety of products are managed through the supermarket concept,formal order releases for such parts are not necessary.

A) True
B) False

Correct Answer

verifed

verified

Which of the following statements regarding MRP in services is true?


A) MRP is for manufacturing only,and is not applicable to services.
B) MRP can be used in services,but only those that offer very limited customization.
C) MRP does not work in services because there is no dependent demand.
D) Services such as restaurant meals illustrate dependent demand,and require product structure trees,bills-of-material,and scheduling.
E) MRP cannot be effectively used in most services.

F) A) and B)
G) B) and C)

Correct Answer

verifed

verified

A manufacturing company is trying to determine the cost of materials used to produce an A.If Fs cost $1 and Ds cost $2 how much does it cost to produce an A (in F and D materials only)?

Correct Answer

verifed

verified

blured image Using an explosion shows that...

View Answer

Four A washers,Five B washers,Two C bolts,and a D bolt are required to make one Grill parts kit.If 100 grill part kits are needed how many more washers will be consumed than bolts?

Correct Answer

verifed

verified

Using MRP explosion gives A:40...

View Answer

Consider the following bill of material.Forty units of Product A are needed.Assuming no on-hand inventory,and no scheduled receipts,explode the bill of material. Consider the following bill of material.Forty units of Product A are needed.Assuming no on-hand inventory,and no scheduled receipts,explode the bill of material.

Correct Answer

verifed

verified

Item A: 40 units;Item B: 40 × ...

View Answer

While ERP may provide a strategic advantage over competitors,it is so complex that many companies cannot adjust to it.

A) True
B) False

Correct Answer

verifed

verified

A popular point to start without math training,the top level in a bill of material is


A) level 0.
B) level 1.
C) level T.
D) level 10.
E) level 100.

F) None of the above
G) B) and C)

Correct Answer

verifed

verified

Which of the following lot-sizing techniques results in the lowest holding costs?


A) lot-for-lot
B) EOQ
C) part-period balancing
D) Wagner-Whitin algorithm
E) the quantity discount model

F) B) and D)
G) B) and C)

Correct Answer

verifed

verified

For the lot-sizing technique known as lot-for-lot to be appropriate


A) future demand should be known for several weeks.
B) setup cost should be relatively small.
C) annual volume should be rather low.
D) item unit cost should be relatively small.
E) the independent demand rate should be very stable.

F) All of the above
G) A) and E)

Correct Answer

verifed

verified

________,unlike MRP,recognizes that departments and machines have limitations on their capacity that must be observed if the schedule is to be realistic.

Correct Answer

verifed

verified

Finite cap...

View Answer

The bill of material contains information necessary to


A) place an order to replenish the item.
B) calculate quantities on hand and on order.
C) convert net requirements into higher level gross requirements.
D) convert gross requirements into net requirements.
E) convert (explode) net requirements at one level into gross requirements at the next level.

F) All of the above
G) A) and B)

Correct Answer

verifed

verified